To set out the procedures to be followed for procuring goods and services for the PROCEED program.
The Finance & Administration Vice-Head of the technical bureau with the assigned financial expert of the BoF are responsible for the organisation of the procurement.
The Administrative Assistance supports the persons in charge of this process and verifies that they have the necessary skills to carry out the tasks and to complete them in a timely manner.
The procurement procedures shall be in accordance with the South Ethiopia Regional State Public Procurement and Property Administration Agency Proclamation No. 25/2016, and with the procurement guidelines for AFD-Financed Contracts in Foreign Countries, dated February 20241).
Goods and services are to be procured on the basis of a competitive selection process, which is transparent, open and fair, and guided by a principle of proportionality (context, risk analysis).
All persons involved shall respect the highest ethical principles during the procurement and the performance of contracts, and not engage in prohibited practices.
Documentation should be prepared, filed and saved as defined in Annex ADM1. Bid documents must be prepared in both Amharic and English for national bids. There is no international bid.
A procurement cannot be split in view of avoiding the limits set out in these guidelines. Artificial contract splitting means the division of the works or supplies or services into several smaller contracts with the aim of achieving lower contract values and as such avoiding a stricter procurement procedure. Should the intervention logic require the division of the contract, the procurement procedure used for the sub-contracts must be identical to the procurement procedure for the contract as a whole.
Tenderers who have legal or economic links to each other should not be assessed as separate bidders in a tendering process.
The Region commits to ensure that, to the best of its knowledge and belief, it is not promoting or engaging in violence, terrorism, or money laundering, nor is it making contracts to any entity that engages in these activities. The Region, supported by the Administrative Assistance, conduct an anti-terrorism screening through the “list of gel” established by the French Ministry of Finance and Economy2) or established by EU3).
The following procurement methods can be used in the procurement of goods/services:
The selection of the procurement method depends on the procedure prescribed in the procurement plan which is based on the type and amount of each procurement. The procurement plan is presented in Annexe Annex ADM2 – A1 with the minimum procurement requirement.
The Procurement Plan is subject to review and change; it must be reviewed at least annually to ensure it reflect programmatic updates and inflation.. However, any modification requires the AFD's approval (no-objection notice).
The thresholds for the PROCEED are fixed in EUR and presented in a table below.
An implementation document defining the current value in ETB of these thresholds shall be drawn up, updated and disseminated by the Administrative Assistance. This is done with a frequency not exceeding once every 6 months, at the request of any financial expert of the RTF or the BoF.
In the event that these thresholds exceed the threshold set out in federal or regional regulations, the lowest threshold will apply, unless a specific exemption is made and signed by the Regional Public Procurement and Property Administration Directorate Director, and validated by a AFD non objection.
| For Good, Service and Works | |
|---|---|
| Procurement method | Threshold (EUR) |
| Quotations | less than 2,000€ |
| Limited tender | More or equal to 2,000€ and less than 100,000€ |
| Open tender | More than 100,000€ |
In the event of a discrepancy between the procurement method set out in the procurement plan and the methods selected in accordance with the above threshold, the most stringent methods shall be applied.
The relevant technical expert(s) is identified based on the type of expense.
Tenderers submitting a tender in response to an invitation must certify that they are not in one of the situations listed in the exclusion and ineligibility criteria in Annexe Annex ADM2 – A3 by signing the administrative part of the tender.
The technical specification shall clearly describe the requirements with respect to:
No specific reference to a particular trademark or name / brand / specific original producer or service provider, unless there is no sufficiently precise way of describing the procurement requirements, in which case words such as “or equivalent” may be included in the specifications.
The technical specifications as well as contracts are including specific social and environmental clauses to be respected by the tenderer and monitored by PROCEED implementer. They are listed in the Sustainability Framework in Annexe Annex GOV3 – A1.
The Annexe Annex ADM2 – A1 defines precisely the characteristics of the tender, selection methods and the AFD no-objection requirement for the planned procurements.
A tender process can be cancelled or bids rejected:
The Annexe Annex ADM2 – A2 defines the minimum information to be included in each key procurement document, and which documents are required for each procurement method.
The Annexe Annex ADM2 – A4 defines the main characteristics of the contract for the water supply contractors.
The choice of these contracts is motivated by the following reasons:
FTCs are contracted to multiply grass. FTCs have a special status in Ethiopia with a mandate to promote new agricultural practices and field trials in Kebele. FTC contracts shall be sole-source, non-competitive, fixed-price contracts (see Annexe Annex ADM2 – A5).
Contract prices are calculated on the basis of the area of grass planted and the number of farms targeted, with unit prices determined at the start of the program and indexed according to the rules set out in Annexe Annex ADM2 – A6.