Pipeline Supervision

This page provides guidance for completing format MF4-F75 “Construction_supervision” regarding pipeline supervision.

PROCEED n° MF4-F74Rev 1.0Pipeline supervision checklistOct-26
V1 Pipes
1.1 Supervisor has the filled format MF4-F73 “pipeline protection”
1.2 Trench is not backfilled on all the length, pipe is installed and layed on ground MF4-M71 §1.f
1.3 No rocks or sharp edges in the bottom of the trench section MF4-M71 §1.c
1.4 Pipes in the trench ar as per sketch map (PN,DN, length) MF4-M71 §1.f
V2 Depth from top of pipe to the ground (at least every 100m, 60cm minimum)
2.1 10 Measures has to be done - MF4-M71 §1.c
V3 Special structures
3.1 Crossings construction is on going, contractor knows dimensions MF4-M71 §3
3.2 If applicable air vent or breather installation is on going as per MF4-M71 §3
3.3 If applicable in rocky area, drystone wall is built as per MF4-M71 §2.a
Supervisor has 1 mandatory validation visit. If one item is not validated correction measures must be agreed with contractor and another visit organized. After validation backfill can be done (except couplings & sensitive areas)