Distribution Box Supervision
This page provides guidance for completing format MF4-F75 “Construction_supervision” regarding DB supervision.
| PROCEED n° MF4-F45 | Rev 1.0 | DB supervision checklist | September 2026 |
| 1 | Foundation excavation & compaction |
| 1.1 | Check yield compare to design requirement MF4-M50 §3 |
| 1.2 | Contractor knows inside dimensions of DB, Height given by design, L=30+15xoutlets number, W=60 for inlet ≤50, W=80 for inlet>50 MF4-M40 §1 |
| 1.3 | Foundation depth is at least 60cm and length is at least = L+0.8m and width = W+0.8m MF4-M15 §1 |
| 1.4 | Drop stone test pass (Mark < 1 cm)MF4-M15 §1 |
| 1.5 | Overflow drainage point is chosen (check slope and surrounding) |
| 1.6 | Contractor knows masonry size & PVC pipes posit. in the foundation MF4-M40 §2 |
| V2 | Preparation for slab casting |
| 2.1 | Masonry height is matching design data (Masonry level = design level - 10cm) MF4-M40 §2 |
| 2.2 | Masonry width and length is matching calculated DB inside dimensions (L & W) MF4-M40 §2 |
| 2.3 | Inlet installed at least 5 cm clerance with the edge of masory MF4-M40 §2 |
| 2.4 | Inlet diameter is matching the sketchmap |
| 2.5 | Outlets as per sketchmap, at least 15 cm clerance with edge of masory MF4-M40 §2 |
| 2.6 | Outlets diameters are matching the sketchmap |
| 2.7 | Outlets air vents are correctly installed (Tee + elbow 20cm apart) MF4-M40 §2 |
| 2.8 | Overflow is installed, end of PVC coupling are precisely located 10cm above masonry top MF4-M40 §2 |
| 2.9 | All pipes are protected from foreign entrance with plastic bag attached by wire MF4-M40 §2 |
| 2.10 | Rebar mesh (20x20cm ⌀8mm) installed around masonry (7-8cm clearance from it) and at bottom slab level MF4-M40 §3 |
| 2.11 | Contractor knows wall & slabs thickness (15cm) and standards for metal door MF4-M15 §3 & concrete (1:2:3) handling MF4-M13 |
| Supervisor has 2 mandatory validation visits. If one item is not validated correction measures must be agreed with contractor and another visit must be organized. If not impossible penalties must be applied (up to contract termination) |